LET'S GIVE IT BACK THE FULLNESS OF A BEATING HEART!

The appearance of the monumental ensemble makes the restoration project exceptionally interesting: the different parts of this church are of different origins. The main body of the church dates from the 13th century, on an earlier, certainly Carolingian, base. The southern transept is flanked by Romanesque apsidioles from the 11th century. The bell tower is from the 16th century. In other words, this “catalogue of architecture”, as a testimony of many epochs, is a remarkable symbol of integration of the past and harmony in diversity.

Today the church lacks its two transepts, like a Latin cross (†) without its arms. It’s not that there aren’t any, but the transepts are separated from the church by massive walls. One, the southern transept, is “open to heaven”. At its far end, the unfinished bell tower needs to be restored and protected against seepage. The project therefore includes the church, the southern transept and the bell tower.

For 5 years, the daily life of the teams will be filled with good and bad discoveries, difficulties and complexities that will have to be overcome as the work progresses.

The Great Recovery of the Church is the central project, the most complex and expensive. It is spread in 3 phases over the 5 years of the full project.

THE PROJECT IN 3 STEPS

Restoring the bell tower 2019 – 2022

 

In the 16th century, Philippe de Lévis, the new abbot of Lagrasse, added a monumental bell tower to the existing church at the end of the south transept. It was a copy of the bell tower of the cathedral of Mirepoix, the abbot’s home town. The building was to be 80 meters high and topped by a spire. The 40-meter spire was never built.

Long-delayed by the covid crisis, this project was divided into several phases:

  • Waterproofing the bell tower ridge
  • Restoring the intermediate floors
  • Restoring the gargoyles, sculptures, pinnacles…

Budget: $1.9 m (€1.8 million)

Lift the south transept 2023 – 2026

 

The southern transept connects the body of the church to the bell tower. Having suffered the ravages of time and man, it is now collapsed and open to the elements. Only a semicircular arch remains. The entrance to the church is blocked. The church is dismantled.

The goal is to restore the transept vault based upon the restored arches, then rebuild the roof’s inner structure and roof itself according to architectural studies. Then reopen the transept to the church.

This exceptional 3-year project includes several components:

  • Demolition of newer parts (plaster vaults, roofs, partitions…)
  • Archaeological excavations
  • Reopening of the transept to the nave
  • Restoration of the transept vaults
  • Reconstruction of the roof structure and roofing

Budget: $3m (€2.8 million)

Restoring the central body of the church 2026 – 2029

 

The 13th-century church body will be restored from floor to roof. This project, which complements that of the transept, will allow us to welcome the ever-increasing number of visitors and offer them a place of worship and prayer.

This 2-year project includes the following:

  • Removal and restoration of stained-glass windows
  • Restoration of roof structure and roofing
  • Restoration of masonry infill
  • Interior improvements: sanctuary furnishings, electricity, in-floor heating

Budget: $3m (€2.8 million)